Earned Value Tester

You are a Project Manager for XYZ company. Your project has a BAC of $1,900,000 and is expected to last 11 months. Currently the project is in month 8 and is 10 percent complete, but the project was expected to be 70 percent complete by this time. You have spent $1,976,000 to complete the work. Calculate the following: